Skip to content
pmecap

Construction

New construction, major renovations and progress draws.

Book a call
PMECAP — QC

The budget drives the draw schedule.

The partner broker organizes the costs, invested equity and draw schedule.

Book a call

Project types

Ground-up construction

Land, budget, schedule and completed value.

Conversion

Purchase, demolition, change of use and required work.

Expansion

Added space, budget and existing debt.

Phased project

Costs, draws and repayment for each phase.

Project completion

Remaining work, revised budget and expected repayment.

What lenders review

Complete budget

The budget covers land, construction, professional fees, interest and contingency.

Committed equity

Invested cash, eligible costs and the timing of contribution determine the draw order.

Cost to complete

After each inspection, remaining funds must cover unfinished work and known commitments.

After construction

The repayment plan identifies a sale or long-term financing.

What gives a lender pause

Cost overrun

Contingency, contracts and available cash must cover cost overruns.

Construction delay

Interest and commitments must remain payable if construction slows.

Incomplete permits

A draw may require a specific permit. Confirm its status before the first draw.

Permanent financing unavailable

Completed value is not enough without a documented sale, leasing plan or permanent loan.

What sets the terms

Amount basis

The amount depends on eligible cost and value. The lender uses the lower limit.

Funding

Completed work and invoices are reviewed before each advance.

Reserve

The reserve covers eligible cost changes without stopping construction.

Term

The term covers construction and the time required to sell or refinance.

Request steps

  1. Review the complete budget
  2. Confirm permits and contracts
  3. Document the equity contribution
  4. Plan the draw requests
  5. Update the cost of remaining work
  6. Prepare the sale or refinancing

What to prepare

  • Plans, specifications, permits and schedule
  • Detailed direct and indirect cost budget
  • Construction contracts and principal bids
  • Evidence of invested equity and sources of funds
  • Current appraisal and value on completion
  • Draw plan, contingency and permanent financing

Loan types

Loan typeWhen this loan type may apply
Construction loanProgress draws follow eligible costs, verified work and invested equity.
Construction-to-permanentA permanent loan replaces construction financing when its conditions are met.
Pre-construction loanIt covers permits, plans and professional fees before the construction loan.
Project completion loanThe amount depends on remaining work, residual value and planned repayment.

Preparing a request, step by step

All guides

Common questions

When must equity be invested?

The lender sets contribution order based on costs, land value and draw conditions.

How are draws authorized?

A documented request, inspection and cost-to-complete confirmation generally precede each advance.

What does contingency cover?

It covers eligible variance. It does not replace missing costs.

Can interest be financed?

An interest reserve may be included when the budget, term and structure support it.

Will an incomplete permit stop financing?

It may become a condition before signing or a draw.

How are presales or preleases treated?

The lender reviews contracts, deposits, conditions and dates before counting them toward repayment.

Book a call about your construction project.

Costs, equity, permits, schedule and long-term financing.

Book a call